Delay Digger

Forensic delay analysis on your own schedule revisions — window by window, separating what slipped because of progress from what slipped because someone edited the plan.

Who it is for. Delay analysts and claims consultants, who currently buy a separate specialist tool. Also contractors defending an extension-of-time claim, and owners’ teams testing a contractor’s delay narrative.

What it is for

When a project slips the argument is never about whether it slipped — it is about why, when, and whose fault. Doing that properly means comparing every monthly update, isolating each window, and testing whether a cause actually moved the finish date. Today that is a specialist product or weeks of manual work.

Against the incumbents

The strongest claim in the product. It implements named AACE 29R-03 methodology — MIP 3.4 half-step bifurcation and MIP 3.7-style but-for verification — inside the same application that holds the schedule, reading the contractor’s own XER updates directly. P6 and MS Project do none of this; the competitor is a separate specialist product.

Delay Digger
Three updates overlaid. Slippage attributed period by period.

What it does

Every line below is in the product today.

  • AACE 29R-03 MIP 3.4 half-step bifurcation

    Re-runs the window-start network with only the window-end progress applied, splitting the finish movement into progress impact and revision impact. The CPM rerun happens off the main thread.

  • Scheduler-verified but-for testing

    Reschedules the later snapshot as a baseline, then once per root cause with that root restored, reporting verified impact days rather than asserted ones.

  • Snapshots from five sources

    The live project, a saved baseline, another project, a saved crash scenario, or an uploaded XER or MSPDI — parsed and analysed without being written to the database.

  • Cascades collapsed into fragnets

    "Thirty activities each slipped thirty days" becomes one root plus its carriers, by walking the link graph back to a root then forward to members.

  • Every activity classified

    Seven critical-path roles — driver, became critical, recovered off the path and so on — and nine claim categories in a fixed priority order.

  • Windows at six granularities

    By snapshot, selected pair, weekly, biweekly, monthly or quarterly — with per-window concurrency detection and a critical-path topology-shift flag.

  • It argues against overstating the claim

    The summed activity slip is labelled cascade-inflated, and the tool tells you not to quote it.

  • It refuses a comparison it cannot defend

    Two snapshots sharing under 20% of activity codes will not produce a first-versus-last claim.

See it on your own schedule.

Send an XER before the call and we will import it and show you Delay Digger running against your data.