Activities

The critical-path Gantt where the schedule is actually built — a virtualised table and timeline that computes your dates from logic, calendars and constraints instead of letting you type them.

Who it is for. Planners, primarily — this is the screen they live in all day. P6-shaped keyboard behaviour means no retraining, and XER in and out means they can still exchange with a client on P6.

What it is for

Planners either pay thousands a seat for P6, or accept a tool that stores dates as text and calls it a schedule. Without a real forward and backward pass, float is guesswork, constraints silently lie, and progress updates never rewrite the plan.

Against the incumbents

Duration derived from quantity divided by production rate is native here and is not a native concept in P6 or MS Project. Beyond that the honest claim is scope in one place rather than a unique algorithm: the same Gantt drives DCMA, crash, forensic delay and Monte Carlo with no export step, in a browser, with no client install.

Activities
Total float, free float, constraint type and calendar as first-class columns.

What it does

Every line below is in the product today.

  • A real forward and backward pass

    Total and free float per activity, including negative float where it belongs.

  • Eight constraint types, with typed violations

    ASAP, ALAP, start and finish no-earlier and no-later, must-start-on and must-finish-on — raising warnings or errors rather than moving silently.

  • Relationship codes normalised defensively

    All four types with leads and lags, accepting P6 shorthand, long form and legacy numeric XER codes.

  • Duration from production rate

    Quantity divided by crew output, with the rate per day, week or month, on working or calendar days, aware of the activity’s own calendar. Not a native concept in P6 or MS Project.

  • Float-path tracing

    From the selected activity — backward, forward, both, or the free-float path — with stepped float cutoffs and a show-only-this-path mode.

  • P6-shaped keyboard

    Field-level undo and redo, fill down, copy and paste of activities, select all — the shortcuts a planner already has in their hands.

  • Several projects in one Gantt

    Projects open as sibling roots with read-only anchors pinned so only the active one flexes, and inter-project logic pulled from an external-links model.

  • A non-destructive what-if sandbox

    Clones the schedule, captures current dates as the scenario baseline, and reschedules live against the real engine without touching the database.

  • Virtualised, and it stays smooth

    Only rows near the viewport render, and wheel zoom is a native non-passive listener coalesced to one model update per animation frame.

See it on your own schedule.

Send an XER before the call and we will import it and show you Activities running against your data.